Quest for ProfitsFollow the filings
CIFRNASDAQAI data centers

Google got a floor.Shareholders didn't.

Cipher signed $16.6 billion of data center rent with Amazon and a leading AI lab, yet its stock fell from a $29.18 record close to $8.98 in four months. Inside its Google warrant agreement is a $430 million floor.

  • Runtime16:50
  • PublishedOct 22, 2026
  • Research as ofOct 17, 2026
  • Sources7
Pick a chapter to jump straight to it. Watch on YouTube ↗

The numbers

What the filings say

$16.6B
Contracted rent, Sept 30, 20266
By the company's own count, in a furnished presentation.
$24.8M
Q2 2026 revenue1
All of it still bitcoin mining; no lease revenue recognized yet.
−$267.5M
Q2 2026 net loss1
Includes a $150.5M non-cash loss on the Google warrants.
$6.0B
Debt principal, June 30, 20261
Against $562M of stockholders' equity: about 10.7× debt to equity.
$3.73B
Restricted cash1
On top of $831.8M of cash. Restricted cash is tied to the projects and their debt.
$17.78
Google's break-even share price3
Below it, Cipher owes Google a top-up in shares or cash. Our own arithmetic: $430M ÷ 24.18M warrant shares.

The breakdown

Who gets paid before shareholders?

The leases and the construction are real and verifiable. The equity carries the risk: heavy debt, rising build costs, a pile of share-convertible claims and a top-up owed to Google if the stock stays under about $17.78.

  1. From Bitcoin miner to AI landlord.

    Cipher went public through a 2021 SPAC as a Texas Bitcoin miner. Its real asset turned out to be its grid connections, which AI tenants need more than miners do.

    Sources 2
  2. The rent is contracted, not collected.

    $16.6 billion of contracted revenue, a 17.3-year average lease term and a projected $843M of average annual net operating income. Those are management's numbers, and the $843M is a projection. At June 30, every dollar of revenue was still mining.

    Sources 61
  3. The bill came first.

    A $267.5M quarterly loss, about $6 billion of debt principal, $964M spent on property and equipment in six months, and Barber Lake now estimated roughly $550M over its original budget.

    Sources 16
  4. Google's $430 million floor.

    Google got 24.18 million warrant shares at one cent for backstopping Fluidstack's lease. If those shares aren't worth $430M when the exercise period starts, Cipher must make up the difference in shares or cash. At the October 16 close of $8.98, that would be roughly 24 million more shares (our one-day estimate).

    Sources 31
  5. More claims on the same company.

    About 40.7 million shares issued on October 16 to retire 2030 notes, plus $1.3B of 2031 and $850M of new 2032 convertible notes (conversion price about $15.31), with physical settlement now the default.

    Sources 45

Two endings

Where this could go

The bull case

Rent arrives and the floor disappears.

  • Data halls deliver on the amended schedule and rent shows up in Q3/Q4 reports.
  • The stock recovers above about $17.78 before the warrant measurement date.
  • Project debt amortizes from rent, and new leases convert the 3.4 GW pipeline.
The bear case

Shares grow faster than rent.

  • Top-up shares, note conversions and at-the-market sales keep raising the share count.
  • Build costs overrun beyond what Cipher has budgeted to bear.
  • Rent goes to debt amortization before equity, and two tenant groups carry nearly all contracted revenue.

Scenarios, not predictions. Not financial advice.

Check our work

Every source

  1. 01
    Form 10-Q: quarter ended June 30, 2026
    Revenue, losses, cash, restricted cash, debt, equity and share count.
    sec.gov · Aug 4, 2026
    SEC filing
  2. 02
    Form 10-K: fiscal year 2025
    Annual results and the history from mining to data centers.
    sec.gov · Feb 24, 2026
    SEC filing
  3. 03
    Google Warrant Agreement (EX-4.1), Section 3.08
    The 24.18M penny warrants and the $430M top-up.
    sec.gov · Sep 24, 2025
    SEC filing
  4. 04
    Form 8-K: 2032 notes and exchange
    The new $850M convertible notes and the 2030 note exchange.
    sec.gov · Oct 14, 2026
    SEC filing
  5. 05
    Form 8-K: conversion price, capped call, share settlement
    The ~$15.31 conversion price, the $28.35 cap and physical settlement.
    sec.gov · Oct 16, 2026
    SEC filing
  6. 06
    Company presentation (8-K, Oct 13, 2026)
    $16.6B contracted revenue, $843M projected NOI, 3.4 GW pipeline, Barber Lake costs. Management's own numbers.
    sec.gov · Oct 13, 2026
    Company presentation
  7. 07
    Daily share prices (Yahoo Finance)
    The $29.18 record close and the $8.98 October 16 close. Fetched Oct 17, 2026.
    finance.yahoo.com · Oct 17, 2026
    Market data
How we researched this

Every financial figure comes from the SEC filings above. Company-presentation figures ($16.6B contracted revenue, $843M projected annual NOI, 3.4 GW pipeline) are management's own numbers, and the $843M is a projection.

The floor math (break-even about $17.78, about $217M of value, about 24M extra shares) is our own calculation on a single day's close. Which date starts the exercise period is defined in the Fluidstack lease, which isn't public.

Also shown in the film: the Fluidstack lease and Google backstop 8-K (Sept 25, 2025), the Barber Lake amendment 8-K (Sept 25, 2026), the Stingray presentation (June 2026) and Form 4s for Bitfury and V3 Holding (Oct 2026), all on Cipher's EDGAR page.

More breakdowns

Keep digging